Dan Burroughs
Jun 9, 20211 min read
Phase one concrete is finished. Paving starts on Thursday
The contractor completed all the concrete work today. So all the sidewalks are completed in phase one of Tenderfoot Street project. The...
6 views0 comments
Dan Burroughs
Jun 4, 20211 min read
Tenderfoot Phase One Nearing Completion
The Contractor had a great week again. Good weather helps construction go well. They completed 90% of the concrete work and completed...
14 views0 comments
Dan Burroughs
Jun 3, 20211 min read
The contractor has completed about 2/3 of the concrete on Tenderfoot Phase One
As of the end of the day, the Contractor has completed about 2/3 of the Phase One Concrete in Tenderfoot Street and the new parking lot...