The resurfacing of the west end of Dillon Ridge Road is tentatively planned for Tuesday, May 18th, 2021. The start date is subject to change due to weather and other construction issues. The project will take approximately 2 days to complete.


Access will be maintained to all of the businesses during construction. More information about the traffic control plan will follow in a subsequent post, as we get closer to the construction dates.



At the March 16th, 2021 Dillon Town Council Meeting, the Town Council awarded the 2021 Dillon Ridge Overlay to A-Peak, Inc. The project involves milling 1.5" of the existing asphalt surface and replacing it with a 2" asphalt overlay. The project will also re-establish all of the paint striping and turn arrows.