Dan Burroughs

May 12, Wednesday Paving Schedule: Village, Schroeder and Main Street

Well, we got through another May snowstorm.

Wednesday and Thursday should have good weather. Here is the revised paving Schedule.


Wednesday (May 12th): the Contractor will pave these streets in the following Order

1) VILLAGE PLACE (Starts around 7:30 am)

2) SCHROEDER

3) MAIN STREET


LA RIVA DEL LAGO RESIDENCES:

The Main Street entrance will be blocked for 3-4 hours while the paving crew is working on this section of Main Street. Please plan to park your vehicles in a nearby parking lot, if you will need your vehicle between 11am and 6pm.


Thursday (May 13th): the Contractor will pave these streets in the following Order

1) FIEDLER AVENUE (Starts around 7:30 am)

2) MAIN STREET - - Remaining Portion if needed


NOTE: On-street parallel parking & diagonal parking will be CLOSED on paving day.